University HV Fault
31st August 2024
We recently received a call during the early hours of a weekday morning from one of our long standing customers; a leading University. They were reporting a loss of power to part of the site and had already contacted the DNO which had confirmed there was no issue with the incoming supply.
We immediately dispatched our on call SAP and 11kV jointer who were on site within a couple of hours. Fault finding testing identified a cable fault between two substations and as the private network was on a ring we were able to sectionalise the fault and restore supplies, much to the delight of the university as the students were beginning to wake!
With site now having a susceptible supply should any other
issues arise, our attention turned to identifying the location of the fault and
getting it repaired as soon as possible. Utilising our in house cable fault
location equipment complete with suitably trained and experienced operatives,
we pinpointed the fault. Using our dedicated civils team, we excavated the area
and uncovered the cause of the fault: an 11kV intermediate straight joint.
We further mobilised an 11kV jointing team and with suitably rated HV cable and joints readily available from our stores, we
cut out the faulty joint and carried out an 11kV insert, and completed commissioning checks, re-establishing the Hv ring to it’s normal operating
status.
Everybody happy and, with the pressure now relieved, we updated
the cable drawings, submitted with all commissioning data and our civils team
followed up the next day to reinstate and ensure site was left tidy
Our Contracting Engineer James Grigg said:
Having all the resources available when needed is just one part of EME Power Systems service levels we pride ourselves in; our customers have the peace of mind when that 2am issue arises EME Power Systems will be there to help.
News Stories
- 21st Anniversary!
- WHO YOU GONNA CALL……
- Welcome Mark Baxter
- Overdue Maintenance
- Customer Feedback
- Larger Than Your Normal EV’s
- Taking the Biscuit
- Benefits of Furans Testing
- Aftermath of Storm Babet
- Emergency Response to Storm Babet’s Disruption
- Welcoming Samantha Collishaw and Reducing Carbon Footprint
- Ardagh Glass Transformer Replacement
- Considering Voltage Management to Help Cut Bills?
- Graham Haydn-Davies Retirement
- LV Sub-Main Fault
- Cable Joint Failure
- Phil Shaw Retirement
- Directional Drilling
- Pre-Planned Maintenance
- Energy Savings Factsheet
- The Benefits of Carrying Out Planned Preventative Maintenance (PPM)
- EME Transformer Stock Saves the Day!
- PARTIAL DISCHARGE TESTING
- Storm Franklyn
- Helping to Mitigate the UK Energy Crisis
- EME Power Systems Helps Company To Join The Recycling Effort
- Christmas Time Switchgear Changes
- Out of Hours Peace of Mind
- EME Power Systems Fast Response for Major Food Manufacture
- Importance of Regular Intrusive Maintenance
- NHS Challenge
- Automated Packaging at Malvern Worcestershire
- Christmas Arrives Early
- Challenge Accepted
- Through these uncertain times...
- Hayley Paddock Joins EME Power Systems
- Challenging Times
- Low Carbon Electricity
- Our excellent installation teams complete essential works
- Fast Response
- Essential Maintenance
- Solution to a tricky transformer replacement
- It's A Cut!
- EME Power Systems Quarterly Update
- Infrastructure Upgrade
- EME Power Systems Continue As Normal
- It's Cold Inside
- Double transformer failure leads to double success
- Steve Harrison Joins the Company
- Class Cancelled
- Now For Something Slightly Different
- Go Green and Save Pounds
- Cable Fault Repair
- ACB
- Time For A Quick Change Around
- Lincoln Prison
- EME Power Systems Renewables
- An Early Summer Break - Out With The Old, In With The New
- EME Power Systems Midweek Break