Taking the Biscuit
23rd May 2024
EME Power Systems have recently been tasked with the replacement of an aged 5 way HV panel comprising of OCB’s and oil filled switches with a new Schneider Genie Evo extensible HV board. The project was undertaken at a well known biscuit factory in London.
With a maximum window of only 72 hours in which to complete the works, a robust plan to deliver the project was formulated, discussed and agreed with the client, thus ensuring that production could recommence and the client’s critical production schedule met.
The cable boxes we compound filled and so our works involved both the burning out of the boxes and the replacement of the cable loops to the local transformers. We also took the opportunity to change the cable boxes at the same time.
The old switchgear removed and the new sited and assembled we reinstated the existing cabling along with the termination of the new. The new auxiliary emergency trip circuits installed and commissioned, the pre calculated protection settings could then be programmed to the protection relays. Following subsequent secondary injection testing we were complete safely ahead of schedule (much to the pleasure of our client).
Following all necessary pre commissioning checks and pressure testing we were able to energise the network and hand control of the system back our client well in advance of the end of 72 hour programme. Our customer taking the opportunity to restart production earlier than they had initially hoped for.
Contracting Engineer James Grigg said:
When a strict time window is given for a shutdown, preparation is the key. We had meticulously planned the works, having numerous spares on site and options for different eventualities. The fact that the works were carried out successfully and well within the deadline, was testament to the hard work of the engineers.
News Stories
- WHO YOU GONNA CALL……
- Welcome Mark Baxter
- Overdue Maintenance
- University HV Fault
- Customer Feedback
- Larger Than Your Normal EV’s
- Benefits of Furans Testing
- Aftermath of Storm Babet
- Emergency Response to Storm Babet’s Disruption
- Welcoming Samantha Collishaw and Reducing Carbon Footprint
- Ardagh Glass Transformer Replacement
- Considering Voltage Management to Help Cut Bills?
- Graham Haydn-Davies Retirement
- LV Sub-Main Fault
- Cable Joint Failure
- Phil Shaw Retirement
- Directional Drilling
- Pre-Planned Maintenance
- Energy Savings Factsheet
- The Benefits of Carrying Out Planned Preventative Maintenance (PPM)
- EME Transformer Stock Saves the Day!
- PARTIAL DISCHARGE TESTING
- Storm Franklyn
- Helping to Mitigate the UK Energy Crisis
- EME Power Systems Helps Company To Join The Recycling Effort
- Christmas Time Switchgear Changes
- Out of Hours Peace of Mind
- EME Power Systems Fast Response for Major Food Manufacture
- Importance of Regular Intrusive Maintenance
- NHS Challenge
- Automated Packaging at Malvern Worcestershire
- Christmas Arrives Early
- Challenge Accepted
- Through these uncertain times...
- Hayley Paddock Joins EME Power Systems
- Challenging Times
- Low Carbon Electricity
- Our excellent installation teams complete essential works
- Fast Response
- Essential Maintenance
- Solution to a tricky transformer replacement
- It's A Cut!
- EME Power Systems Quarterly Update
- Infrastructure Upgrade
- EME Power Systems Continue As Normal
- It's Cold Inside
- Double transformer failure leads to double success
- Steve Harrison Joins the Company
- Class Cancelled
- Now For Something Slightly Different
- Go Green and Save Pounds
- Cable Fault Repair
- ACB
- Time For A Quick Change Around
- Lincoln Prison
- EME Power Systems Renewables
- An Early Summer Break - Out With The Old, In With The New
- EME Power Systems Midweek Break